KZN’s new airport on track

2008-10-24 00:00

Although significant progress has been made over the past year, very tight deadlines have to be met to ensure that KwaZulu-Natal’s new international airport at La Mercy opens on time — on May 1, 2010.

According to officials from the Airports Company of South Africa (Acsa) who briefed Transport Minister Jeff Radebe on the progress of construction during a site visit yesterday, almost R3 billion has been spent on the project so far.

The R6,8-billion airport also boasts a facility known as the Dube TradePort (DTP), elevating the total cost to about R8 billion.

“The project is on track for completion [and] I must also say that there are very tight targets that we must meet,” conceded Bongani Maseko, group executive of airport operations at Acsa.

He said they are in the process of appointing a German consultancy firm to advise Acsa.

This firm was involved in a similar “change-over” of airports in Münich.

“I can say that we have already started interacting with international carriers from the East [and] carriers from Europe,” said Maseko.

Acsa will undertake a four-month testing and commissioning exercise once the airport is completed at the end of next year.

About 3 500 construction jobs have been created so far.

This figure will grow to about 6 000 at the peak of construction activity.

Acsa believes that about 5 000 full-time jobs will be created once the facility is opened.

The airport will have an annual capacity of 7,5 million passengers in the first phase.

The site is located between Sibiya Casino and the Tongaat Toll Plaza, using the N2 (northbound) freeway as a reference point.

The briefing yesterday was followed by a sod-turning ceremony on the road that provides access to the site, off the R102.

Colin Naidoo, communications and brand manager at Durban International Airport, said that the first steel supports for the roof truss were recently placed on the departures slab.

He added that the basement level of the multi-storey parkade has already been completed.

“The runway and taxiways construction with the lower sub base on the runway has been completed and the upper sub base already commissioned. With the control tower being the most visible facility if travelling from the north, the construction of the cab of the control tower is complete.

“The cargo terminal is [at a] very advanced [stage] now,” added Sean van der Valk, project manager at Acsa.

Join the conversation!

24.com encourages commentary submitted via MyNews24. Contributions of 200 words or more will be considered for publication.

We reserve editorial discretion to decide what will be published.
Read our comments policy for guidelines on contributions.

24.com publishes all comments posted on articles provided that they adhere to our Comments Policy. Should you wish to report a comment for editorial review, please do so by clicking the 'Report Comment' button to the right of each comment.

Comment on this story
0 comments
Comments have been closed for this article.

Inside News24

 
/News

Book flights

Compare, Book, Fly

Traffic Alerts
There are new stories on the homepage. Click here to see them.
 
English
Afrikaans
isiZulu

Hello 

Create Profile

Creating your profile will enable you to submit photos and stories to get published on News24.


Please provide a username for your profile page:

This username must be unique, cannot be edited and will be used in the URL to your profile page across the entire 24.com network.

Settings

Location Settings

News24 allows you to edit the display of certain components based on a location. If you wish to personalise the page based on your preferences, please select a location for each component and click "Submit" in order for the changes to take affect.




Facebook Sign-In

Hi News addict,

Join the News24 Community to be involved in breaking the news.

Log in with Facebook to comment and personalise news, weather and listings.