Tongaat Mall battle of the engineers

2014-02-14 18:49

(AP)

Multimedia   ·   User Galleries   ·   News in Pictures Send us your pictures  ·  Send us your stories

Durban - It became a battle of the engineers on Friday at the labour department's commission of inquiry into the collapse of the Tongaat Mall, outside Durban, last year.

The developer's current engineer claimed there were serious problems with the previous engineer's design plans.

Engineer Rob Young said he received the plans for the mall from structural engineer Andre Ballack.

A portion of the mall, which was under construction, collapsed on 19 November, killing two people and injuring another 29.

Ballack was the structural engineer at the time the mall collapsed, and had been appointed by Gralio Precast.

Young, who was the lead design engineer for Durban's King Shaka International Airport and has since been appointed by Gralio Precast to investigate what went wrong, said he and his team had viewed the plans.

"We found material defects that could have led to the collapse," said Young.

Young, and at least three other engineers - Ballack, an engineer from the eThekwini metro municipality, and an engineer from the Engineering Council of SA - are expected to be questioned by the commission in early June.

That, however, will not happen until there has been a site visit by all engineers on 10 March and the controlled removal of debris takes place.

Young explained to the commission that it was necessary to remove the collapsed slab to examine pillars and other items of interest in a bid to determine what caused the collapse.

Sagged by 70mm

The labour department's occupational health and safety manager Phumudzo Maphaha, who heads the three-man commission, said that barring anything unexpected, he hoped to present his findings by the end of August.

Earlier this week site foreman Ronnie Pillay told the commission that in the days preceding the collapse one of the concrete slabs sagged by 70mm.

Apart from the sagging slab, he said he had raised concerns over the thickness of the pillars, as well as the lift shaft.

During testimony of the safety consultant hired by Gralio Precast it emerged that there had never been any health and safety audits.

Permission to build the mall was never obtained and the eThekwini municipality had obtained a court order stopping the development.

However, building continued unabated and the mall was scheduled to open in March this year.

Read more on:    durban  |  tongaat mall collapse
NEXT ON NEWS24X

SHARE:

Read News24’s Comments Policy

24.com publishes all comments posted on articles provided that they adhere to our Comments Policy. Should you wish to report a comment for editorial review, please do so by clicking the 'Report Comment' button to the right of each comment.

Comment on this story
11 comments
Add your comment
Comment 0 characters remaining

Inside News24

 
/News
Traffic Alerts
Horoscopes
Aquarius
Aquarius

There is a strong desire to connect and participate in group related gatherings. You may feel the need to bond or connect with a...read more

There are new stories on the homepage. Click here to see them.
 
English
Afrikaans
isiZulu

Hello 

Create Profile

Creating your profile will enable you to submit photos and stories to get published on News24.


Please provide a username for your profile page:

This username must be unique, cannot be edited and will be used in the URL to your profile page across the entire 24.com network.

Settings

Location Settings

News24 allows you to edit the display of certain components based on a location. If you wish to personalise the page based on your preferences, please select a location for each component and click "Submit" in order for the changes to take affect.




Facebook Sign-In

Hi News addict,

Join the News24 Community to be involved in breaking the news.

Log in with Facebook to comment and personalise news, weather and listings.