New tank farm planned for Ngqura

2018-10-17 06:02
An artist’s impression of the tank farm at the Port of Ngqura.             Photo:SUPPLIED

An artist’s impression of the tank farm at the Port of Ngqura. Photo:SUPPLIED

Multimedia   ·   User Galleries   ·   News in Pictures Send us your pictures  ·  Send us your stories

TRANSNET National Ports Authority (TNPA) updated stakeholders at an engagement session recently regarding progress made on establishing the Port of Ngqura as a new petroleum trading hub for Southern Africa.

TNPA has already completed phase one of the infrastructure required to service the site. This includes the construction of a new access road from the N2 to the location where Oil Tanking Grindrod Calulo Holdings (OTGC), the private terminal operator, will build the new tank farm.

TNPA also completed the detailed design of the new Port Entrance Plaza and the new main access road, including the pipe line servitude that will form the link between the new tank farm and the port.

Phase two of the project is expected to commence next month and includes the landside development, forming the link between the tank farm and the berth.

According to the Build, Operate and Transfer (BOOT) agreement, OTGC will plan, fund, construct, maintain and operate the new liquid bulk handling facility in the port.

The concept engineering design and the relevant surveys have been completed and construction is due to start next month.

This OTGC development in the Port of Ngqura will also make way for the decommissioning and remediation of the existing liquid bulk facilities in the Port of PE. As part of the cut over strategy and subsequent to the commissioning of the Ngqura facility, the PE Tank Farm operators will wind down operations over a period of four months. During this period it is envisaged that no further related shipments will be received in the Port of PE.

According to the statement, TNPA is working closely with the PE Tank Farm operators to compile a decommissioning and remediation plan, which once approved by Department of Environmental Affairs, will be executed after the four month winding down period.

“The development period of 24 months will commence on November 1, this year and we look forward to having an operational terminal at the Port of Ngqura by November 1, 2020,” the statement read.

Join the conversation!

24.com encourages commentary submitted via MyNews24. Contributions of 200 words or more will be considered for publication.

We reserve editorial discretion to decide what will be published.
Read our comments policy for guidelines on contributions.
NEXT ON NEWS24X

Inside News24

 
/News
Traffic Alerts
Traffic

Jobs in Cape Town [change area]

Jobs in Western Cape region

Cluster Financial Manager

Cape Town
Network Finance
R950 000.00 - R1 000 000.00 Per Year

SQL Reporter

Cape Town
Communicate Cape Town IT
R10 000.00 - R12 000.00 Per Month

Reporting Accountant

Cape Town
Network Finance Professional / Prudential
R310 000.00 - R360 000.00 Per Year

Property [change area]

There are new stories on the homepage. Click here to see them.
 
English
Afrikaans
isiZulu

Hello 

Create Profile

Creating your profile will enable you to submit photos and stories to get published on News24.


Please provide a username for your profile page:

This username must be unique, cannot be edited and will be used in the URL to your profile page across the entire 24.com network.

Settings

Location Settings

News24 allows you to edit the display of certain components based on a location. If you wish to personalise the page based on your preferences, please select a location for each component and click "Submit" in order for the changes to take affect.




Facebook Sign-In

Hi News addict,

Join the News24 Community to be involved in breaking the news.

Log in with Facebook to comment and personalise news, weather and listings.