AS IT HAPPENED: Gordhan concludes Eskom briefing, appeals to South Africans to reduce electricity demand

2019-03-19 10:29

Eskom chairperson Jabu Mabuza says the operational side of Eskom requires “crisis reaction” as well as time and speed to fix the current load shedding situation.

[Live stream courtesy of SABCnews.com]

JOHANNESBURG, SOUTH AFRICA ? DECEMBER 06: Public e
LIVE NEWS FEED

Jump to
bottom

Last Updated at 18:11
19 Mar 13:23

We only have ourselves to blame - Eskom COO

Eskom only has itself to blame for the lapse of a contract for early detection of maintenance failures, according to Eskom chief operations officer (COO) Jan Oberholzer.

There are currently seven generating units which have broken down due to boiler tube leaks as Eskom struggles to maintain its ageing power fleet.

Oberholzer said the contract for early detection of faults in the wide network of tubing inside boilers lapsed 18 months ago and had not yet been renewed. They are hoping to have a new tender in place by the end of the week.


19 Mar 12:48

ICYMI:

COLUMN: 4 reasons the ANC has only itself to blame for the Eskom crisis

The political capturing of Eskom started in earnest in 2008 when the company started handing out tenders and contracts for its new build program which at that time was worth around R385bn over five years, writes James-Brent Styan.The Eskom crisis is the ANC's fault.

Sorry. It just is.

And no, I'm not even referring to all the warnings over the years that the country would run out of electricity; warnings that were largely ignored. That was long ago. I'm talking about the current crisis. Let me explain with the facts.


19 Mar 12:19

19 Mar 12:19
Gordhan says feedback is important, promises to have more information and answers within next 10 to 14 days. Says they’re determined not to go past stage 4 load shedding.

19 Mar 12:19

19 Mar 12:18

Gordhan does an overview:

We fully understanding of disruptions load shedding has caused.

We will communicate better.

We are doing an appeal to South Africans to go back to helping to meet demand, which he says is direclty linked to undertaking maintenance. 



19 Mar 12:17

19 Mar 12:16

19 Mar 12:15

Gordhan says they’ll be talking to Auditor-General and Treasury to allow for faster procurement processes.

"Will avoid risk of these processes becoming corrupt."


19 Mar 12:08

19 Mar 12:06
CEO Phakamani Hadebe says they have bought between 20 million litres and 25 million litres of diesel (for emergency gas turbines). Have exhausted the supply. There’s no diesel in SA, except for cars and small utilities.

19 Mar 12:06

19 Mar 12:05
Hadebe: 65% of coal was bought short term. Going back to long term contract. 

19 Mar 12:03

Eskom sets aside R50bn over 5 years for maintenance

Eskom has set aside R50bn over the next five years for maintenance as ageing infrastructure is unable to keep up with electricity demand, according to the power utility’s CEO Phakamani Hadebe.

Hadebe said Eskom had been using its maintenance spend previously on generation alone but will now also focus on transmission and distribution networks.

He said there had been a decline in spend in maintenance in the last few years and the previous administration at Eskom had pushed the power system hard to keep the lights on.


19 Mar 11:57

Mabuza: The board has asked me that without taking sides on debate, as it is a bit inappropriate and disingenuous in the IPPs (Independent Power Producers).

The cost of energy, there's a R30bn provided for IPPs. As far Eskom is concerned, what we buy on IPPs, we recoup from the turf. IPPs are not the source of the problem. 


19 Mar 11:50
Gordhan: We are a recovering democratic government and loadshedding in the result of that.  We'll get it right in the next year or two.

19 Mar 11:47

19 Mar 11:45
Hadebe says they have set aside R50bn for maintenance in next five years. Not just for generation, will also spend on maintaining transmission and distribution networks. 

19 Mar 11:45
Mabuza admits they create “more questions” when they answer questions. Agrees with Minister Gordhan they could have communicated better. Promises to improve from today.

19 Mar 11:44

19 Mar 11:42
Mabuza: It's important to know that there are still hardworking men and women at Eskom. It's only through them that we can do these things.

19 Mar 11:40

19 Mar 11:39
Gordhan says there’s a push back(against exposure of corruption) so people don’t go to jail.

19 Mar 11:38
Gordhan says state capture leaves clear patterns in many SOE’s. Moved money from maintenance to capital expenditure. “There’s still a lot of accountability to take place”.

19 Mar 11:37

19 Mar 11:37

Eskom needs 'crisis reaction' - Eskom's Mabuza

Eskom chairperson Jabu Mabuza says the operational side of Eskom requires “crisis reaction” as well as time and speed to fix the current load shedding situation.

The media was taken through several slides showing the gap between Eskom’s installed capacity of 48 000 megawatts and average available supply of 28 000 megawatts.

Seven generating units are currently out of the system due to boiler tube leaks.This is the single biggest cause of plant breakdowns.

The power utility’s fleet is ageing and some of the power stations are 50 years old and the average is 37 years old.


19 Mar 11:34
Spending of maintenance has decreased over time. 

19 Mar 11:34
Mabuza says he is unable to talk about what previous CEO has claimed, in answering media question.

19 Mar 11:34
Mabuza says the maintenance spend should not have been on a downward trend as Eskom’s power fleet became increasingly old.

19 Mar 11:32

19 Mar 11:24

19 Mar 11:22

19 Mar 11:22

Markets LIVE: Rand struggles to gain ground on back of load shedding

"The rand has remained largely flat, trading in a tight range between R14.38 and R14.50, where it is expected to remain," Peregrine Treasury Solutions's Bianca Botes said.


19 Mar 11:21
The last option is load shedding. 

19 Mar 11:20

Mabuza: The processes that are in government are not geared up for the speed that is required. Money intended for plant maintenance was never used for this purpose. 

"We don't have the time, we don't have the money"


19 Mar 11:17
Mabuza: You have not for the last 5 years done maintainance. This equipment has worn, has torn. There is no other answer but fixing it.

19 Mar 11:17
Mabuza: I see Eskom in 2 streams: the routine stream, the process you need to follow to make things work. Then there is a crisis stream. That crisis would need a crisis reaction methodology. We need time, we need speed to get equipment and people. And you need money.

19 Mar 11:14
"We do need time with the equipment." - Mabuza. 

19 Mar 11:13

19 Mar 11:13
"Structural, operational and financial - how Mabuza desribes Eskom power struggle. 

19 Mar 11:10
Boiler tube leaks are visible They need time to cool down in order to be fixed.

19 Mar 11:09

19 Mar 11:09

19 Mar 11:08
Coal power plants of 40-50 years old still being used.

19 Mar 11:07

19 Mar 11:04

No end in sight to load shedding

-    Shortage of around 10 000 MW daily.

-    Will have clarity on exact interventions and timeframe in two weeks.

-    Eskom/task team/government hoped to have stabilised grid by end of January, but new challenges emerged.

-    Main issue is lack of maintenance at power stations, not done properly for last decade, now breaking down.

-    Between Feb 2017 and Feb 2018 system tripped  300 times, between Feb 2018 and Feb 2019 it tripped 495 times.

-    Four options: (1) import electricity (2) burn diesel (spent R4,5 bn the last four months to keep turbines going) (3) build new power stations and (4) load shedding.

-    Problems structural, financial, operational.

-    Internal resistance against reform and restructuring process, state capture elements still prevalent.


19 Mar 11:03

19 Mar 11:00

'No magic formula to solve power crisis' - Gordhan

There is no magic formula to solve the current load shedding crisis and the Minister of Public Enterprises Pravin Gordhan is unable to say when the rotational blackouts will be over.

Gordhan was briefing the media on Tuesday, along with senior Eskom officials as the country entered its fifth consecutive day of Stage Two to Stage Four load shedding.

“At this point in time, we are still getting a better grasp of the technical problems,” Gordhan said.


19 Mar 10:59
Gordhan admits government has not communicated adequately about load shedding. Promised to improve in the next few days 

19 Mar 10:57

Jump to
top

SHARE:

Inside News24

 
/News
Traffic Alerts
Traffic
There are new stories on the homepage. Click here to see them.
 
English
Afrikaans
isiZulu

Hello 

Create Profile

Creating your profile will enable you to submit photos and stories to get published on News24.


Please provide a username for your profile page:

This username must be unique, cannot be edited and will be used in the URL to your profile page across the entire 24.com network.