Share

Service provider appointed to get Charlotte Maxeke hospital up and running

accreditation
0:00
play article
Subscribers can listen to this article
The Charlotte Maxeke Hospital was gutted by a fire in April. The hospital is still closed.
The Charlotte Maxeke Hospital was gutted by a fire in April. The hospital is still closed.
Gallo Images/Sharon Seretlo

NEWS


Takgalang Consulting is in the process of drawing up the missing sections of Charlotte Maxeke Academic Hospital floor plans. The missing plans mean that one of Gauteng’s largest hospitals cannot be issued with a fire safety certificate, forcing the provincial department of infrastructure development to yet again delay the reopening of the healthcare facility.

The department says it is unable to provide a reopening date for the hospital, but the oncology unit is still expected to reopen on July 5.

“The plans will only be submitted to the City of Johannesburg once the service provider has completed the process,” department spokesperson Bongiwe Gambu said.

Gauteng authorities initially closed the hospital for seven days when parts of it were damaged by fire in April. Then it was announced that the oncology unit would reopen early this month, but that did not happen.

Gambu at the time said that “the delay was caused by the approval of the radiation and oncology unit by the City of Johannesburg, which was dependent on the acquisition of fire doors which were long lead items”.

While July 5 was set as the prospective reopening date for the oncology unit, it was contradicted by acting Health Minister Mmamoloko Kubayi-Ngubane on June 18 when she said that the hospital would reopen in phases starting this week.

READ: Charlotte Maxeke hospital reopening pushed back – again

Closed tender process ‘to circumvent corruption’

Takgalang Consulting is currently scanning and taking measurements of the hospital buildings before recreating the missing sections of the plans, Gambu told City Press on Wednesday.

She said that in an effort to mitigate corruption and wrongdoing, the process undertaken to appoint the service provider was through a closed tender.

“We invited service providers on our panel – grade 7, 8 and 9 contractors. After that the process underwent all the supply chain management requirements,” she explained.

The continued closure of Charlotte Maxeke Academic Hospital has raised concerns about the impact it has had on the public health system, as the province is currently in the thick of its third Covid-19 infections wave.

‘R23m goes up in flames’

On April 16, a blaze – in which an estimated R23 million worth of personal protective equipment and other medical items were destroyed – took hold of a section of Charlotte Maxeke Academic Hospital and a decision was subsequently made to shut it down and transfer patients to other medical facilities.

READ: Makhura calls for local state of disaster to reopen Charlotte Maxeke Hospital

Two months later and the hospital remains closed after it was revealed that lack of adequate structural plans delayed its reopening.

Kubayi-Ngubane last week said that “the other issue that was a challenge was around the fire doors that needed to be manufactured and that took longer because without those the certificates would have taken longer to be issued”.

‘Fire safety laws were different back then’

According to reports, a fire safety audit at the hospital was signed off weeks before the blaze tore through parts of the hospital.

The hospital fire and safety team also met in March, according to the Gauteng department of health.

Asked about how a fire safety audit was signed off in the absence of building plans, Gambu explained that this was due to the fact that the hospital is housed in an old building “which opened its doors in 1979”.

“At that time, the laws governing building plans were different to what is in place currently.”

“In particular, organs of state were not required to submit architectural plans to a local authority. The National Building Regulations and Building Standards Act now requires all public, private and residential buildings to have approved plans, which are then submitted to the local authority [municipality].”

READ: Office heater believed to be behind Bara hospital blaze

Meanwhile, as hospital beds continue to be scarce, Chris Hani Baragwanath Academic Hospital on Sunday experienced a “small fire breakout at its laundry area”. The hospital is under severe pressure as it has been forced to accommodate patients from Charlotte Maxeke.


facebook
twitter
linkedin
instagram

Palesa Dlamini 

Journalist

+27 11 713 9001
palesa.dlamini@citypress.co.za
www.citypress.co.za
69 Kingsway Rd, Auckland Park
We live in a world where facts and fiction get blurred
In times of uncertainty you need journalism you can trust. For 14 free days, you can have access to a world of in-depth analyses, investigative journalism, top opinions and a range of features. Journalism strengthens democracy. Invest in the future today. Thereafter you will be billed R75 per month. You can cancel anytime and if you cancel within 14 days you won't be billed. 
Subscribe to News24
heading
description
username
Show Comments ()
Latest issue
Latest issue
All the news from City Press in PDF form.
Read now
Voting Booth
With confirmation from government that convicted rapist and murderer Thabo Bester escaped from prison last May and is currently on the run, what is your view of SA's justice system?
Please select an option Oops! Something went wrong, please try again later.
Results
The justice system is overwhelmed
14% - 5 votes
It's a joke
8% - 3 votes
Corruption is destroying SA
78% - 29 votes
Vote